Posted on: September 18th, 2013 by admin No Comments

DISTRIBUTION CENTRE RACKING INSTALLATION

Being an owner managed organisation allows us to be extremely flexible in our approach to working with customers.

The project was particularly interesting, as we needed to ensure the operation remained unaffected by the racking installation and at the same time, execute a phased handover programme.

The first milestone in the programme required us to handover 2000 pallet spaces in just 5 days, which I am pleased to say we achieved with our S.E.I.R.S. approved installation teams. The installation comprises of a 600m2 anti collapse mesh screen, rack upright protection, mesh panel decking, labelling and steel partitioning, all of which needed to be co-ordinated into the programme to ensure the deadlines were achieved.

For further information, please visit www.logicalstorage.co.uk or telephone 0845 689 1300.